- Client
- Suncor Energy
- Location
- 130 km north of Fort McMurray, AB
- Year
- 2006
- Services
- Aggregates
In 2006, we crushed 1.5 million tonnes of granular material for the Stage 3 expansion of Suncor Energy’s Firebag oil sands project, about 130 km north of Fort McMurray, Alberta.
Firebag is Suncor’s in-situ operation, where bitumen is recovered from deep underground using steam rather than open-pit mining. Stage 3 was a major expansion of the operation, adding new plant facilities and well pads to increase production.
Working more than 2,000 km by road from Fort Frances, our crushing spread and crew supplied the granular material for the expansion.